The City of Toronto awarded Clearway Construction Inc. contract 24ECS-LU-06SU for watermain and water-service replacements, bikeway construction and major road resurfacing along University Avenue. The approved contract value is approximately $13.5 million.

The overall project extends from College Street to approximately 120 metres north of Queen Street West. The watermain construction portion currently identified by the City extends from Armoury Street to College Street.

The project was deferred to coordinate with Metrolinx construction and preparations for the 2026 FIFA World Cup. Construction began in the revised schedule in August 2026, with completion anticipated in spring 2027.

 